Construction
Eight phases · 2004 – 2007
George Petrides bought the raw land, put in the road and services, designed the house and acted as general contractor.
The house coming together
Sixteen photographs, September 2004 to September 2007. Select any photograph to step through them at full size.
















Eight phases, in detail
The crews, the craft and the work inside the walls.
Phase 2
Foundation
September 2005
Forms were set and the foundation walls poured in the autumn of 2005.
Phase 3
Framing
November 2005
The frame rose in November 2005: floor decks, walls, roof and the rooms in outline.
Phase 4
Sheathing & Windows
January – March 2006
Sheathed and roofed through the winter; windows set into their openings; ductwork and partitions inside.
Phase 5
Clapboard & Greek Revival Trim
March – April 2006
The exterior took on its Greek Revival dress: clapboard, corner boards, a pilastered door surround, and an arched window with full entablature.
Phase 6
Masonry & Roofing
April – September 2006
Brick fireboxes and chimneys were laid up and the roof shingled.
Phase 7
Interiors
April – October 2006
Insulation, plaster, the wide pine floors, the stairs and the baths: the rooms moved from frame to finish.
Phase 8
Grounds & Completion
May 2006 – 2007
The grounds were cleared and graded, the house finished in 2007, and the lawns, walls and plantings settled in.